Capacity is the one supplier claim buyers never verify and the one that decides whether a season is made or missed. It is not a feeling and it is not a square-metre figure; it is lines multiplied by shifts multiplied by effective hours multiplied by efficiency, and then constrained by whichever single station is slowest. Once you can compute that yourself, the conversation changes completely: instead of asking "can you handle our volume," you ask "how many line-days does our order consume and where does it sit in your queue," which is a question with an answer. Peak season is where this matters, because congestion is not a shortage of total capacity in the industry — it is a shortage of capacity in the specific eight weeks when everyone needs it.
This guide covers the capacity equation term by term, why big headline numbers are meaningless without a bottleneck and an efficiency assumption, the actual mechanism of pre-holiday congestion, why reserving a slot beats negotiating a price, how to convert a forecast into priority, how split orders protect capacity without creating a warehouse problem, what a capacity commitment should say, how to judge whether a supplier is honest about its queue, the real shape of the holiday calendar, how many line-days your order needs, where overtime stops working, and a planning calendar for a seasonal programme. The production baseline at QUANZHOU JUNYUAN BAGS — custom waterproof bag production since 2014, 4,950 m² SGS-verified facility — is MOQ 500 pieces per style, sampling in 6–10 working days and bulk in 35–50 days, FOB Xiamen.



The capacity equation, term by term
Production capacity planning starts with an equation that every supplier knows and few buyers ask for: available capacity equals active lines, multiplied by shifts per day, multiplied by effective hours per shift, multiplied by an efficiency factor, multiplied by the number of working days in the window. Then one more step that most people skip — the result is capped by the bottleneck station, not by the fastest one. Peak season scheduling is the discipline of planning against that capped number rather than the uncapped one.
Take a realistic cell. A welded waterproof bag line might run twenty-two to twenty-eight stations: cutting, panel preparation, welding or taping, assembly, hardware fitting, trimming, branding, inspection and packing. If welding takes ninety seconds per unit and every other station takes less, the line’s theoretical output is forty units per hour. Nobody achieves theoretical output. Changeovers, material waits, rework, absenteeism and first-article checks consume real time, so a healthy efficiency factor for a mixed custom programme sits around sixty-five to eighty per cent, and below sixty per cent for a line running many short runs.
| Term | Typical value in a welded bag cell | What moves it |
|---|---|---|
| Active lines | Four to twelve depending on facility size | Capital, floor space, and how many are actually staffed this week |
| Shifts per day | One, or two in peak season | Labour availability and overtime cost, not management preference |
| Effective hours per shift | Eight scheduled, seven to seven and a half productive | Breaks, setup, material handling and end-of-shift cleanup |
| Efficiency factor | Sixty-five to eighty per cent on long runs, fifty to sixty-five on short mixed runs | Style count, changeover frequency, material readiness and operator experience |
| Bottleneck station rate | Welding or taping, commonly sixty to one hundred and twenty seconds per unit | Construction complexity, fixture condition and laminate behaviour |
| Working days in window | Twenty-two to twenty-six per month, fewer around holidays | The published factory calendar, which is knowable in advance |
Run that cell and you get a number that is often an order of magnitude smaller than the figure printed on a website. A single line at eighty per cent efficiency, seven and a half effective hours, one shift and a ninety-second bottleneck produces roughly two hundred and forty units a day, about five thousand a month. A facility claiming two hundred thousand pieces a month is therefore making a statement about many lines running two shifts with high efficiency and long runs — possible, but only if the product mix supports it, and a custom waterproof programme with many styles and short runs does not.
The useful consequence for a buyer is that you can compute your own order’s consumption of that capacity. Ten thousand pieces on a line that yields two hundred and forty a day is forty-two line-days, roughly two working months on one line. Asking "how many line-days does my order need, and which line and week has it been assigned" is a far more informative question than anything about total capacity, and it is the question that exposes a supplier who has overbooked. The wider calendar into which those line-days must fit is mapped in our lead time guide.
Why "we have very large capacity" tells you nothing
The phrase is used as reassurance and functions as the opposite, because it is unfalsifiable. Three specific reasons make headline capacity numbers close to useless for a buyer making a decision.
- It is measured at a different product mix. Capacity quoted for long runs of one simple style does not exist when your programme is six styles of eight hundred pieces each, because changeover time eats the day and short runs never reach steady-state efficiency.
- It ignores the bottleneck. Adding sewing heads to a line whose welding station is saturated increases work-in-progress, not output. Output is set by the slowest station, and most headline numbers are computed from the sum of the fastest ones.
- It is stated as if the queue were empty. Capacity is not available capacity. A line that can produce two hundred and forty units a day and is booked solid for the next nine weeks has, for you, a capacity of zero until week ten.
There is a fourth reason that is behavioural rather than technical. Suppliers systematically overstate capacity because buyers reward it. A buyer choosing between a supplier who says "we can do eight thousand a month for you specifically" and one who says "we are enormous" will, more often than they should, pick the enormous one — and then discover in October that enormous was a marketing adjective. The honest answer is always narrower and always more useful, which is why a supplier willing to name a number per week for your specific construction is worth more than one quoting a facility total.
The verification is straightforward and takes one email. Ask for three things: the number of lines that will run your construction, the daily output per line for that construction, and the current booking position for the window you need. Suppliers who answer all three concretely are telling the truth about capacity. Suppliers who answer with a facility total twice more are not going to tell you when they fall behind either. The full set of questions worth asking on site is in our supplier audit checklist, and capacity honesty is the item most audits skip.
The real mechanism of peak season congestion
Peak season congestion is widely described as everyone ordering at once, which is true and explains nothing. The mechanism is queueing, and it has a specific shape in this industry that buyers can plan around once they see it.
The pre-holiday surge works like this. Every exporter with a Q1 delivery commitment wants goods loaded on a vessel before the shutdown. That compresses roughly twelve weeks of normal despatch into six to eight weeks, on a production system that was already running at eighty to ninety per cent utilisation. Utilisation above about eighty-five per cent is where queueing theory turns unfriendly: waiting times do not rise linearly with load, they rise steeply, because there is no slack left to absorb variation. A line running at ninety-five per cent utilisation does not deliver five per cent less than one running at ninety per cent; it delivers unpredictably and late, because any disruption — a material delay, a quality hold, an absent operator — has nowhere to go.
Then three amplifiers stack on top. Material suppliers hit their own peak simultaneously, so fabric and hardware lead times stretch by one to three weeks exactly when production can least absorb it. Vessel space tightens, so a shipment that misses its booking waits seven to twenty-one days for the next. And quality gates get compressed, which is the dangerous one — a line under schedule pressure is a line where weld parameters get adjusted faster than they should and inspection sampling gets quietly thinner. The failures surface in February as returns rather than in December as delays.
The planning response is not clever, but it is effective: shift your own order earlier rather than asking the factory to work harder. Moving a programme two weeks earlier in the queue often buys more certainty than any amount of expediting later, because you are buying slack rather than chasing throughput. Our seasonal planning guide covers the commercial side of that calendar; the production side is simply that the earlier slot is the cheaper one in every sense.
Reserving capacity matters more than locking price
Buyers spend weeks negotiating a two per cent price concession and no time at all on whether their goods will be made in the window they need. That is almost always the wrong allocation of effort, and the arithmetic is not close.
A price concession of two per cent on a fifty thousand dollar order is one thousand dollars. A schedule slip of four weeks on a seasonal programme costs the season: the goods arrive after the selling window, inventory carries into the next year at a discount, and the shelf or listing position goes to someone else. In seasonal categories the realistic cost of missing the window is measured in tens of per cent of the order value, not two. The concession is noise; the slot is the signal.
- Price is renegotiable every cycle; a missed season is not recoverable at any price.
- A supplier who has reserved capacity for you will protect your order when everyone else is squeezed, because it is already scheduled rather than merely promised.
- Capacity reservation changes behaviour upstream: material can be ordered against a slot, tooling can be built against a slot, and the sample can be scheduled against a slot.
- Locked prices without reserved slots are the standard arrangement, and the standard outcome is a supplier who honours the price on goods delivered late.
This does not mean price is irrelevant — it means the sequencing is wrong when price is settled first. The productive order is: agree the volume and window, get the slot, then optimise price within the slot. Suppliers price more generously for volume they can plan, because planned volume is cheaper to make. The tactics that work in that sequence are set out in our negotiation guide, and the terms that should carry the commitment are in the contract terms guide.
Converting a volume forecast into scheduling priority
A forecast is the currency you already hold and rarely spend. Suppliers allocate scarce slots to customers who give them something to plan against, and a buyer who can say what they will need next quarter is worth more to a factory than a buyer who merely pays on time.
The minimum useful forecast is a rolling three-month view by style, with a confidence band rather than a false precision. "Style A, 3,000 to 4,000 units in Q1, 2,500 to 3,500 in Q2" is far more useful than a single number, because it tells the supplier what to prepare for and what the downside is. Add the two things suppliers actually need: which styles share materials, and which ones need tooling. A shared-material forecast means fabric can be bought once against a range rather than style by style, which is a genuine cost and time saving the supplier can price into your programme.
Then attach a commitment to part of it. A forecast with no commitment is a wish; a forecast where the first month is a firm purchase order and the following two months are indicative is a plan. The standard structure is a rolling firm window — four to eight weeks firm, eight to sixteen weeks indicative — which gives the supplier enough certainty to book material and reserve a slot while leaving you room to adjust. Most suppliers will reserve capacity against the firm window and hold a provisional slot against the indicative one.
What you get back is worth naming explicitly: a provisional line assignment, an earlier material order, and a named contact who tells you when the queue is tightening. Ask for all three when you hand over the forecast, not later. Buyers who do this are the ones who get the phone call in September saying the window is closing — which is worth more than any discount. Our reorder guide shows how this turns into a standing schedule once the programme is running.
Split orders: holding capacity without inflating inventory
The tension every seasonal buyer faces is that capacity wants a big early commitment while cash and inventory want a small late one. Splitting the order is the standard resolution, and it works better than most people execute it.
| Approach | Capacity effect | Inventory effect | Best when |
|---|---|---|---|
| Single large order, early slot | Strongest claim on the line | Highest carrying cost and obsolescence risk | Proven styles with stable demand |
| Two splits, one slot each | Good, if both slots are booked up front | Moderate; first drop sells while second is made | New styles where demand is uncertain |
| Three or four drops against one reserved block | Best balance: one capacity reservation, staged releases | Lowest, because releases follow real sell-through | Programmes with any demand uncertainty at all |
| Small orders placed reactively | Weakest — you are always at the back of the queue | Lowest inventory, highest stock-out risk | Never, in a constrained season |
The structure that works is a reserved block with staged releases. You commit to a total volume — say twelve thousand units across the season — and reserve the capacity for all of it in one negotiation, then release it in three or four production orders with defined specification-freeze dates. The supplier gets a plan, which is what lets them hold the slot; you get to adjust the mix and timing as real demand arrives, which is what keeps inventory honest.
Three conditions make it function. First, the total must be genuinely committed, not aspirational — a reservation against a volume you may not take is a reservation you will lose when the season tightens. Second, each release needs its own specification freeze, because a change to drop three cannot be allowed to reopen drop two. Third, agree the treatment of unreleased balance: what happens if you release only eight thousand of twelve thousand by the cut-off date, and whether the supplier may reallocate the remaining slot.
There is a cost, and it is worth pricing rather than discovering. Split runs sacrifice some line efficiency — each setup and changeover is paid for again — and smaller runs may cross price breaks. A realistic penalty for splitting a run into three is two to five per cent on unit price, which is cheap insurance against holding a season of inventory you guessed wrong about. The freight side compounds this, and our shipping and logistics guide covers how split shipments change the container economics.
What a capacity commitment should say in writing
A capacity conversation that ends with "no problem, we can handle it" has produced nothing enforceable. The commitment needs six elements, and each one should appear in the order confirmation or contract.
- The window: a defined production start week and a defined goods-ready week, not a duration. "Production begins week of 14 October, goods ready for loading by 25 November" is enforceable; "35 to 50 days" only tells you how long it runs once it starts.
- The volume and mix: total units per style, because a line scheduled for one style runs at a different rate than the same line across four.
- The consequence: what happens if the supplier misses the goods-ready date — a remedy, a penalty, or a freight upgrade at their cost. Without a consequence, the date is a preference.
- The dependencies: what the supplier needs from you, by when, for the slot to hold — deposit, artwork approval, material confirmation.
- The reallocation rule: whether the slot may be given to another customer if your deposit or approval is late, and with what notice.
- The queue disclosure: an honest statement of current booking in the relevant window, so both parties are planning from the same reality.
The window element deserves emphasis because it is where most disputes originate. A lead time of 35–50 days tells you nothing about when your goods will be ready if the line is fully booked; only an assigned start week does. Insist on a calendar date attached to a week number, and ask for confirmation in writing when that week is still valid two weeks before it opens. A supplier who confirms the slot twice is a supplier who is managing it.
Note that a commitment cuts both ways. If you have been given a slot and then delay artwork, change the specification or miss the deposit date, the slot is morally and practically forfeited — the supplier has turned away other work to hold it. Buyers who treat reserved capacity as a free option find that their reservations quietly stop being honoured. Terms that allocate this fairly are covered in the contract terms guide.
Reading whether a supplier is honest about its own queue
This is the highest-value judgement in the whole capacity conversation, and it can be made in one exchange. The signals are consistent because the underlying incentives are consistent: a supplier who has overbooked will avoid specifics, and one who has not will volunteer them.
| What you ask | Honest answer | Warning sign |
|---|---|---|
| How many lines will run my construction? | A number, and which ones | A facility total, or "many lines" |
| What is the daily output per line for this style? | A range with the efficiency assumption stated | A monthly total with no derivation |
| What is booked in the window I need? | A percentage, and when it is likely to tighten | "We always manage" or "no problem" |
| When must you have my deposit to hold the slot? | A date, with the reason | No date, because no slot exists |
| What happens if I need to move two weeks later? | An explanation of what that displaces | "Flexible" with no consequence |
Behaviour over time is the stronger evidence. A supplier who tells you on week two that they are waiting on your artwork is managing your programme; a supplier who says everything is fine until week eight and then reveals a three-week slip was never holding a slot at all. Ask for a weekly status line during the run — one sentence on where the order sits — and judge the supplier by whether the bad news arrives early.
Two structural checks help as well. Ask how they handle two customers who both need the same week, which forces the allocation policy into the open. And ask what they do when a material delay hits: a supplier with a real plan will describe pre-booking critical material against a forecast, while one without will describe calling the mill. Capacity honesty and material planning are the same competence viewed twice.
The working calendar: holidays and shutdowns in their true shape
Holiday shutdowns are the most predictable disruption in the industry and the most consistently under-planned. The published dates are known a year in advance, and the shape of the disruption is always wider than the official closure.
| Event | Official closure | Effective disruption | Planning implication |
|---|---|---|---|
| Chinese New Year | Roughly seven to fifteen days depending on year | Three to five weeks including the run-up surge and the gradual return | Goods for Q1 must be on a vessel before the shutdown; brief signed roughly four months earlier |
| National Day period | Around one week | Ten to fourteen days including travel and restart | An October delivery needs the order complete by mid-September |
| Summer peak for northern-hemisphere seasons | No closure | Six to ten weeks of congestion from roughly June to August | Book slots eight to twelve weeks ahead of need |
| Pre-Christmas retail push | No closure | Four to six weeks of freight and production pressure | Freight bookings, not production, are usually the binding constraint |
The gradual return is the part buyers model wrong. Production does not resume at full rate on the day the holiday ends; the workforce returns over one to three weeks, and even when bodies are present the line takes days to reach steady efficiency with new or reassigned operators. Assuming full output on day one after a shutdown is a reliable way to lose ten days.
The run-up surge matters just as much. In the three weeks before a shutdown, every customer wants their goods out, quality gates get compressed and overtime becomes the norm. Orders scheduled to complete in that window are the ones most likely to have corners cut, so the defensive move is to schedule completion at least two weeks before the shutdown rather than in the final days. Labour and working-hour practice during those periods is also a compliance question, and the social compliance audit guide explains what auditors look for when overtime has been heavy.
How many line-days does your order actually need
This is the calculation that turns capacity from a claim into a number you can negotiate with, and it takes about five minutes. Estimate the per-unit bottleneck time for your construction, divide it into effective daily minutes, apply the efficiency factor, and divide your quantity by the result.
| Construction | Bottleneck time per unit | Units per line-day at 75% efficiency | Line-days for 5,000 units |
|---|---|---|---|
| Roll-top dry bag, welded, minimal assembly | Sixty to ninety seconds | Two hundred and forty to three hundred and sixty | Fourteen to twenty-one |
| Welded backpack, multi-panel, padded harness | Three to five minutes | Seventy to one hundred and ten | Forty-five to seventy |
| Insulated cooler backpack | Four to six minutes | Fifty-five to ninety | Fifty-five to ninety |
| Technical pack with moulded back panel and multiple zips | Six to ten minutes | Thirty-five to sixty | Eighty-five to one hundred and forty |
Read the last column and the scale of the problem becomes visible. A five thousand piece order of complex technical packs consumes well over three months of a single line. If you need it in six weeks, you need three lines running it concurrently — which is a very different request, and one that has to be made months earlier than buyers typically make it. This is why the "how many line-days" question gets honest answers: it translates your volume into the supplier’s actual constraint.
Then add the non-production days that everyone forgets. Setup and first-article validation occupy one to three days at line start. Inspection and packing add two to five. Material waiting, if procurement is not complete, adds whatever it takes. A programme that needs forty line-days therefore occupies closer to fifty calendar days, and the gap between those two numbers is where most schedules actually fail. The seven-stage view in our lead time guide gives the fuller decomposition.
Where overtime and extra shifts stop working
When a season tightens, the first lever a factory reaches for is more hours, and it works — up to a point that is lower than most buyers assume. Understanding where it stops explains why "just add a shift" is not an answer to a capacity shortfall.
A second shift adds close to a full shift of output if it is properly staffed, supervised and supplied with material, which is a real condition rather than a formality. Night shifts typically run five to fifteen per cent below day-shift efficiency because supervision is thinner, support functions are reduced and defects are found later. Overtime on the existing shift adds perhaps ten to twenty per cent for a few weeks, then degrades: fatigue raises defect rates, absenteeism rises and accident risk increases. Sustained overtime beyond roughly sixty hours a week is where quality visibly deteriorates, and it is also where compliance auditors start asking questions that can cost you more than the units were worth.
The hard ceiling is the bottleneck station. Overtime on every station except the welder increases work-in-progress, floor congestion and rework loops while output stays flat. Doubling output at the bottleneck usually requires a second fixture and a trained operator, and fixtures have their own lead time — often three to six weeks for a welded construction. That is the real answer to why a factory cannot simply absorb a doubled order in October: the constraint is equipment and trained people, not willingness.
The buyer-side implication is that the best time to ask for more capacity is before the peak, not during it. A supplier told in June that Q4 needs double Q3 can order fixtures, train operators and book material. The same request made in September can only be met with overtime, and overtime is the least reliable form of capacity that exists. Working-hour limits and their audit treatment are covered by the International Labour Organization, whose standards are the reference most social compliance programmes are built on.
Dual sourcing as capacity insurance
Dual sourcing is usually discussed as a price lever and is far more valuable as a capacity lever, provided it is structured so that it does not destroy the very priority it is meant to protect.
- Split by role, not evenly: one supplier holds sixty to seventy per cent as the primary and earns your forecast; the second holds the remainder and stays qualified and warm. Even splits mean neither supplier values you.
- Qualify the second supplier properly — samples, tooling, material specification and audit — before you need them. An unqualified backup is not capacity insurance, it is a wish.
- Keep the specification portable: a documented construction, material callouts and a sealed reference sample are what allow a second source to produce an acceptable unit quickly.
- Be honest about the arrangement. Suppliers usually know when they are one of two, and pretending otherwise turns a manageable conversation into a trust problem.
- Accept the cost. Dual tooling, duplicated qualification and smaller runs per supplier cost real money, typically three to eight per cent. Price it as insurance against a missed season, not as an inefficiency to be eliminated.
The failure mode to avoid is the reactive second source: discovering in September that your supplier is late and then trying to stand up an alternative. Qualification alone takes four to eight weeks for a welded construction, which means the alternative arrives after the season. The second source has to exist before it is needed, and it has to have made something recently.
There is also a middle path that suits mid-sized programmes: reserve the capacity with one supplier and pre-qualify a second for the following season, refreshing the qualification annually with one small order. That keeps the option alive at a fraction of the cost of running both concurrently, and it means a serious disruption costs you one season of transition rather than one season of nothing.
A capacity planning calendar for a seasonal programme
Everything above collapses into a backwards calendar. The table assumes a programme delivering into a northern-hemisphere peak season; shift the months for other markets, but the intervals are the same.
| Weeks before goods must ship | Action | Why at this point |
|---|---|---|
| Twenty-eight to thirty-two | Share a rolling forecast by style and confirm the supplier can hold a provisional block | Fixture and tooling lead times run three to six weeks; material runs four to eight |
| Twenty to twenty-four | Convert the first block into a firm order with a defined production window in writing | This is when the slot stops being provisional and starts displacing other customers |
| Sixteen to twenty | Freeze specification and artwork; confirm material is booked against the slot | Late material is the most common cause of a lost slot |
| Twelve to sixteen | Confirm the slot is still valid; ask explicitly whether the queue has tightened | Two confirmations catch overbooking while there is still time to react |
| Eight to twelve | Production starts; request a weekly one-line status | Bad news delivered at week ten is manageable; at week two it is not |
| Four to six | Book vessel space and confirm the goods-ready date against the booking | Freight, not production, is frequently the binding constraint in peak |
| Zero to two | Inspection, packing and loading | Compressed quality gates here are the origin of most February returns |
Two intervals in that calendar are load-bearing and routinely compressed. The forecast at twenty-eight to thirty-two weeks is what lets fixtures and material be ordered, and a programme that starts at twenty weeks is already paying for expediting. The slot confirmation at twelve to sixteen weeks is the last point at which a schedule problem can be fixed cheaply — after that, every fix costs money and none of them fully work.
If you want to plan against real numbers rather than estimates, review our own process from first enquiry through sampling into bulk production and send us your forecast, target window and style mix. Minimum order quantity is 500 pieces per style, sampling takes 6–10 working days, bulk production runs 35–50 days from sample approval and deposit, quotations are issued FOB Xiamen, and capacity is reserved against a firm window rather than a hope. Planning practice across that sequence follows the body of knowledge maintained by ASCM, whose planning frameworks are the reference for the scheduling methods described here, with process discipline following ISO 9001 principles.
Frequently Asked Questions
Q1. How is factory production capacity actually calculated?
Lines multiplied by shifts, effective hours per shift, an efficiency factor and working days in the window, then capped by the bottleneck station. Output is set by the slowest station, not the sum of the fastest.
Q2. Why is a headline monthly capacity figure misleading?
Because it is measured at a different product mix, ignores the bottleneck station, and describes capacity rather than available capacity. A fully booked line has, for you, no capacity at all.
Q3. What is a realistic efficiency factor for a custom bag line?
Sixty-five to eighty per cent on long runs of one style, and fifty to sixty-five per cent on short mixed runs, because changeovers and material waits consume the day.
Q4. Why does everything slip before Chinese New Year?
Roughly twelve weeks of normal despatch compresses into six to eight, on a system already at eighty-five to ninety per cent utilisation. Above that level, waiting times rise steeply rather than linearly.
Q5. Is reserving capacity more important than locking price?
Almost always. A two per cent price concession is noise against the cost of missing a selling season. Agree volume and window first, get the slot, then optimise price inside it.
Q6. What should a rolling forecast contain to be useful?
Three months by style with confidence bands, plus which styles share materials and which need tooling. A firm first month with two indicative months is the standard structure.
Q7. Does splitting an order protect my place in the queue?
Yes, if you reserve one block and stage the releases. Commit the total, book the capacity once, then release in drops with separate specification freezes.
Q8. What does splitting a run cost me?
Typically two to five per cent on unit price, from repeated setup and smaller runs crossing price breaks. It is cheap insurance against holding a season of inventory you guessed wrong about.
Q9. What must a capacity commitment say in writing?
A defined start week and goods-ready week, volume and mix per style, the consequence of missing, your dependencies, the reallocation rule, and an honest statement of current booking.
Q10. How can I tell whether a supplier is overbooked?
Ask how many lines will run your construction, the daily output per line, and what is booked in your window. Specific answers indicate honesty; facility totals and "no problem" indicate otherwise.
Q11. How long does production really take to resume after a holiday?
The official closure is the smaller part. The workforce returns over one to three weeks and the line needs days to reach steady efficiency, so assume three to five weeks of effective disruption.
Q12. How many line-days does a 5,000 piece order need?
Fourteen to twenty-one for a simple roll-top dry bag, forty-five to seventy for a multi-panel welded backpack, and eighty-five to one hundred and forty for a technical pack with moulded panels.
Q13. Why can the factory not just add a second shift?
A second shift works if staffed, supervised and supplied, but output is still capped by the bottleneck station. Doubling throughput there needs another fixture and a trained operator, which takes three to six weeks.
Q14. How much can overtime really add?
Ten to twenty per cent for a few weeks, then it degrades through fatigue, defects and absenteeism. Sustained overtime beyond about sixty hours a week is where quality visibly deteriorates.
Q15. Is dual sourcing worth the cost?
As capacity insurance, often yes. Expect three to eight per cent for duplicated tooling and smaller runs, and split by role rather than evenly so your primary supplier still values the account.
Q16. When is the last point I can fix a schedule problem cheaply?
Twelve to sixteen weeks before goods must ship. After that, every remedy costs money and none fully work, which is why the confirmation request at that point matters.
Q17. Does reserving capacity obligate me as the buyer?
Yes. If you delay artwork, change the specification or miss the deposit after a slot has been held for you, the slot is practically forfeited because the supplier turned away other work to keep it.
People Also Ask
How do you calculate factory production capacity?
Lines times shifts times effective hours times efficiency times working days, capped by the bottleneck station. Always ask for output per line for your specific construction.
Why do bag orders slip before Chinese New Year?
Every exporter compresses twelve weeks of despatch into six to eight, and material and vessel capacity tighten at the same time. Shift your order earlier rather than expediting later.
What is more important, price or production slot?
The slot. A two per cent price concession is trivial against missing a selling season, which costs tens of per cent of order value.
How far ahead should I book production capacity?
Share a forecast twenty-eight to thirty-two weeks out and convert to a firm order with a defined window twenty to twenty-four weeks out.
Can a factory just add a shift to handle my peak order?
Partly. Output is capped by the bottleneck station, and doubling it needs another fixture and a trained operator, which takes three to six weeks.
Is splitting my order into drops a good idea?
Yes, if you reserve one capacity block and stage releases with separate specification freezes. Expect a two to five per cent unit price penalty for repeated setups.